The Ongoing Issue with the Capital's Scaffolding-Clad Hotel?

Scaffolding surrounding a hotel on a busy street
The metal framework encasing the hotel on George IV Bridge may not be fully removed until 2027.

Positioned on the busiest tourist streets in the heart of Scotland's heritage-rich city centre stands a giant structure of construction framework.

For half a decade, a prominent hotel on the intersection of Edinburgh's Royal Mile and a major bridge has been a plastic-wrapped eyesore.

Visitors are unable to reserve stays, foot traffic are funneled through narrow walkways, and establishments have abandoned the building.

Restoration efforts started in 2020 and was originally estimated to last a short period, but now frustrated residents have been told the framework could persist until 2027.

Extended Timelines

Sir Robert McAlpine (SRM), the lead company, says it will be "towards the end" of 2026 before the earliest portions of the scaffold can be dismantled.

A local authority figure a council official has called it a "eyesore" on the area, while preservation advocates say the work is "very troublesome".

What is going on with this seemingly endless project?

A clean, modern hotel facade without scaffolding
Scaffold-free - how the hotel looks without its covering on the brand's website.

A Troubled History

The 136-bedroom hotel was developed on the site of the old local government offices in 2009.

Projections from when it initially debuted under the Missoni Hotel banner, put the development expense at about £30m.

Remedial efforts started soon after the start of the coronavirus outbreak with the hotel itself shut for business since 2022.

Part of the road and a significant portion of footpath leading up to the intersection of the historic street have been rendered unusable by the project.

Walkers going to and from the Lawnmarket and a neighboring street have been required single-file into a tight, enclosed passage.

Seafood restaurant a popular spot departed from the building and transferred to another city in 2024.

In a release, its operators said construction activity had obliged them to modify the restaurant's facade, adding that "patrons merited more".

It is also home to popular eatery a chain – which has hung large banners on the scaffold to remind customers it is open for business.

The hotel under construction in 2008 Scaffolding going up on the hotel in 2020
Pictures show the the building being built in September 2008 (left) and the project beginning in 2020 (right).

Slipped Schedules

An report to the council's transport and environment committee in early this year suggested that the process of "revealing" the frontage would begin in February, with a complete dismantling by the close of the year.

But the contractor has said that is not the case, citing "highly complicated" structural challenges for the delay.

"We expect starting to take down sections of the scaffold towards the end of the coming year, with subsequent enhancements proceeding afterwards," the company commented.

"We are collaborating closely with the relevant stakeholders to ensure we deliver an improved site for the community."

Local and Conservation Frustration

A conservation official, director of heritage body the an advocacy group, said the work had reinforced the city's reputation of being "leisurely" for development.

She said those working on the project had a "civic responsibility" to lessen inconvenience and should integrate the work into the city's streetscape.

She said: "It causes the pedestrian experience in that part of town exceptionally challenging.

"It is puzzling why there is not a try to integrate it into the street view or create something more creative and cutting-edge."

People walking through a narrow, covered walkway next to scaffolding
Tourists have been required to walk down a confined sheltered walkway on a section of the road.

Continued Work

A official statement said work on "ideas to enhance the appearance the site" was ongoing.

They added: "We acknowledge the annoyances felt by nearby inhabitants and shops.

"This has been a long and drawn-out process, highlighting the intricacy and magnitude of the remedial work required, however we are focused on finishing this essential work as soon as is feasible."

The council leader said the council would "continue to put pressure" on those involved to wrap up the project.

She said: "This structure has been a problem for years, and I echo the exasperation of locals and area enterprises over these persistent hold-ups.

"Nonetheless, I also recognize that the company has a responsibility to make the building structurally sound and that this repair has proved to be extremely complicated."

JF